How our projects progress:
March 2014
Began preliminary route review.
May 2014
Held Supply informational meetings and contacted landowners.
May 2014 — February 2015
Conducted environmental and engineering studies of preferred route.
July 2014
Began FERC NEPA pre-filing process.
August 2014
Held additional public meetings, including Empire.
November 2014
Held FERC Supply scoping meetings.
March 2015
Submitted FERC 7(b)/7(c) filing.
May 2015
Held FERC Empire scoping meeting.
May 2015
Began right-of-way acquisition.
May 2015 – December 2016
Completed additional studies.
February 2017
Received FERC 7(b)/7(c) certificate.
As early as fiscal 2022
Planned in-service date.